The Supreme Court has upheld the Bombay High Court’s decision setting aside the ₹8,415 crore write-down of Yes Bank’s Additional Tier-1 bonds during the lender’s 2020 reconstruction. The ruling leaves bondholders’ contractual rights intact, including the terms governing coupon payments.

The dispute turned on the final reconstruction scheme approved in March 2020. A write-down clause had appeared in an earlier draft, but it was not included in the notified final scheme. The court held that the administrator could not use powers beyond that final framework to extinguish the bonds after the reconstruction scheme had taken effect.

The judgment also examined the RBI’s Basel III framework for AT1 instruments. According to the ruling as reported, any write-down under that framework would have needed to occur before the reconstruction scheme became operative, not afterward. The Supreme Court dismissed the appeals challenging the Bombay High Court’s order.

The decision resolves the legality of this specific Yes Bank write-down. It should not be read as a general guarantee for all AT1 bonds, which remain loss-absorbing instruments whose terms and applicable regulatory framework can differ. Investors and issuers will need to assess the judgment alongside the governing documentation in any future dispute.