- Category AMoEFCC on the recommendation of the Expert Appraisal Committee for the sector
- Category BSEIAA on the recommendation of the SEAC; B1 needs an EIA report, B2 does not
- Time limitsTerms of Reference 60 days, public hearing 45 days, appraisal 60 days, decision 45 days (paragraphs 7 and 8)
- After clearanceHalf-yearly compliance reports on 1 June and 1 December (paragraph 10)
Related topics
The statute, rules and portals the page relies on. Check them before acting: fees, forms and time limits change by notification.
The Notification is subordinate legislation. Section 3(2)(v) of the Environment (Protection) Act 1986 lets the Central Government restrict the areas in which industries, operations or processes may be carried out, and Rule 5(3) of the Environment (Protection) Rules 1986 sets the procedure for doing so by notification. The first EIA Notification came in January 1994; the present one, S.O. 1533(E) of 14 September 2006, replaced it and has been amended many times since, most recently on the validity of clearances in April 2022. Its Schedule lists 39 kinds of project in eight groups: mining and extraction of natural resources, primary processing, materials production, materials processing, manufacturing and fabrication, service sectors, physical infrastructure including environmental services, and building, construction, townships and area development.
The obligation attaches before any construction work or preparation of land begins, other than securing the land. It attaches to three kinds of event in India: a new project in the Schedule; an expansion or modernisation of an existing project that crosses a Schedule threshold or changes the process or technology; and a change in the product mix of an existing project beyond the terms of its clearance. A project that falls below every threshold in the Schedule needs no clearance under the Notification, though it still needs the consents of the State Pollution Control Board and any forest, wildlife or coastal approval that its site requires.
The project proponent
Applies in Form 1 on PARIVESH, engages the accredited consultant, pays for the studies, answers for the data submitted (paragraph 8(vi)), attends the public hearing and appraisal, and carries the clearance conditions for the life of the project.
The accredited consultant
A consultant organisation accredited by NABET under the Quality Council of India for the sector and category concerned, which collects the baseline data, prepares the EIA report and Environment Management Plan and appears before the committee (paragraph 13).
The regulators
The State Pollution Control Board holds the public hearing; the SEIAA and its SEAC appraise and decide Category B; the Ministry of Environment, Forest and Climate Change and its sectoral Expert Appraisal Committees appraise and decide Category A.
Related topics
The statute, rules and portals the page relies on. Check them before acting: fees, forms and time limits change by notification.
| Feature | Category A | Category B |
|---|---|---|
| Who grants the clearance | The Central Government in the Ministry of Environment, Forest and Climate Change | The State Environment Impact Assessment Authority (SEIAA), a three-member body the Central Government notifies for each state for a term of three years |
| Who appraises | A sectoral Expert Appraisal Committee (EAC) constituted by the Ministry | The State Expert Appraisal Committee (SEAC) constituted by the Central Government for the state |
| Screening | None: every Category A project needs an EIA report | The SEAC decides at screening whether the project is B1 (EIA report required) or B2 (no EIA report; appraised on Form 1, the pre-feasibility report or conceptual plan and the committee's own inquiry) |
| Public consultation | Required unless the project is in the exempt list in paragraph 7(i)III | Required for B1 projects unless exempt; never required for B2 |
| Examples of thresholds | Coal or lignite thermal power of 500 MW and above; cement plants of one million tonnes a year and above; hydroelectric projects of 50 MW and above; nuclear power and asbestos mining of any size | Thermal power below 500 MW; cement below one million tonnes a year; hydroelectric projects of 25 MW and above but below 50 MW; building and construction projects of 20,000 square metres of built-up area and above (item 8(a), appraised as B2 on Form 1A) |
| Where the file lives | PARIVESH, with the agenda and minutes of every EAC meeting published | PARIVESH, with the SEAC and SEIAA agenda and minutes published for the state |
The General Condition
Location can move a project up a category. Under the General Condition in the Schedule, a Category B project located in whole or in part within the distance the condition fixes (5 kilometres since the amendment of 25 June 2014) from the boundary of a protected area notified under the Wild Life (Protection) Act 1972, a critically polluted area identified by the Central Pollution Control Board, a notified eco-sensitive area, or an inter-state or international boundary is appraised at the Central level as Category A, subject to the exceptions the amended condition carries. The Supreme Court considered how the condition applies to building and township projects in Confederation of Real Estate Developers' Associations of India v. Union of India (2025).
Related topics
The statute, rules and portals the page relies on. Check them before acting: fees, forms and time limits change by notification.
Application
The proponent files Form 1 on PARIVESH (Form 1A as well for building and township projects under item 8) with a pre-feasibility report, or a conceptual plan for construction projects, and a draft Terms of Reference for the EIA study.
Stage 1: screening (Category B only)
The SEAC examines Form 1 and the pre-feasibility report and classifies the project as B1, which must produce an EIA report, or B2, which need not. The decision follows the Schedule, the sector guidelines and the sensitivity of the site.
Stage 2: scoping
The EAC or SEAC settles the Terms of Reference: the impacts to be studied, the baseline data to be gathered (one full season of primary data other than the monsoon for most sectors) and the special studies required. It conveys the ToR within 60 days of receipt of Form 1; if it does not, the ToR the proponent proposed are deemed final. The Ministry's standard ToR for each sector apply alongside the specific additions.
The EIA study
The accredited consultant collects the baseline, models the impacts, examines alternatives and writes the draft EIA report and Environment Management Plan in the Appendix III structure, with a summary in the local language for the hearing.
Stage 3: public consultation
The State Pollution Control Board holds a public hearing at or near the site within 45 days of the proponent's request, after a 30-day public notice in a national and a regional daily; the District Magistrate or a representative not below the rank of Additional District Magistrate presides, the proceedings are video-recorded, and the Board forwards them to the regulatory authority within 8 days of the hearing (Appendix IV). Written responses from other concerned persons are collected in parallel. The proponent then addresses the material concerns in a final EIA report.
Stage 4: appraisal
The EAC or SEAC scrutinises the final EIA report, the public hearing proceedings and the proponent's presentation in a meeting whose agenda and minutes are public, and recommends grant with conditions or rejection within 60 days of receiving the final report.
Decision
The regulatory authority conveys its decision within 45 days of receiving the recommendation. It normally accepts the committee's view; if it disagrees it must send the matter back with reasons for reconsideration. Where no decision issues in time, the proponent may proceed as though the clearance had been granted or refused in the terms of the committee's final recommendation (paragraph 8).
Time limits and exemptions in paragraphs 7 and 8
The Notification counts 60 days for the Terms of Reference, 45 days for the public hearing, 60 days for appraisal and 45 days for the decision, so that a complete final EIA report should produce a decision within 105 days. Public consultation is dispensed with for the projects paragraph 7(i)III lists: modernisation of irrigation projects, projects inside an approved industrial estate or park, expansion of roads and highways that needs no further land, building, construction, township and area development projects under item 8, every B2 project, and projects of national defence and security or other strategic concern. For an expansion, modernisation or change of product mix the committee decides on due diligence whether further studies and a fresh consultation are needed (paragraph 7(ii)). Deliberate concealment or false or misleading information leads to rejection of the application or cancellation of a clearance already granted (paragraph 8(vi)).
Related topics
The statute, rules and portals the page relies on. Check them before acting: fees, forms and time limits change by notification.
The accreditation scheme grades a consultant organisation sector by sector and for Category A or B, and names the coordinators and functional area experts it may deploy. The Ministry had required accredited consultants by office memorandum since December 2009; the 2016 amendment made the requirement part of the Notification, and committees now return a report prepared outside the accredited scope. The consultant appears before the EAC or SEAC with the proponent, and the last chapter of every report discloses the organisation, its accreditation and the experts who worked on each functional area. Responsibility for the data nevertheless stays with the proponent: the application is in its name, the undertaking on the accuracy of the information is its own, and paragraph 8(vi) visits any concealment or false statement on the clearance rather than on the consultant.
- Introduction. Purpose of the report, identity of the proponent and the consultant, the regulatory setting and the scope of the study fixed by the Terms of Reference.
- Project description. Type, need, location with maps, size and magnitude, process and technology, raw materials, water and energy balances, waste streams and the construction schedule.
- Description of the environment. The baseline: air, noise, water, soil, land use, ecology and biodiversity, and the socio-economic setting within the study area, with the methodology and the season of monitoring.
- Anticipated impacts and mitigation. The predicted change in each component during construction and operation, modelled where the ToR require it, and the measures that avoid, reduce or offset each impact.
- Analysis of alternatives. Technology and site alternatives considered, and the reasons for the choice made, including the no-project option.
- Environmental monitoring programme. Parameters, locations, frequency and the organisation that will monitor, feeding the half-yearly compliance reports after clearance.
- Additional studies. Public consultation outcomes, risk assessment and disaster management plan, social impact assessment and the resettlement and rehabilitation plan where land or people are displaced.
- Project benefits, cost benefit analysis, Environment Management Plan, summary and disclosure. The remaining chapters: physical and social benefits, an environmental cost benefit analysis where scoping asked for one, the EMP with budget and institutional arrangements, a summary and conclusion, and the disclosure of the consultants engaged.
Baseline data decides the timetable
The Terms of Reference normally require one full season of primary monitoring, excluding the monsoon, at the stations the committee specifies. A study that begins late in a season, or that leans on secondary data where primary data were required, is the commonest reason a committee defers appraisal and asks for a fresh season. The season of monitoring is therefore the critical path of the whole clearance.
Related topics
The statute, rules and portals the page relies on. Check them before acting: fees, forms and time limits change by notification.
| Matter | Provision | Rule |
|---|---|---|
| Validity | Paragraph 9, as amended by S.O. 1807(E) of 12 April 2022 | The period within which construction or production is to commence: 10 years for most projects, 13 years for river valley projects, 15 years for nuclear power projects and 30 years for mining projects, with the extension the paragraph allows on an application made before expiry. |
| Compliance reporting | Paragraph 10 | Half-yearly compliance reports on the clearance conditions, in hard and soft copy, to the regulatory authority on 1 June and 1 December each year. The reports are public documents and the latest one is displayed on the regulatory authority's website; the Ministry's regional offices, the SEIAA and the State Board monitor compliance. |
| Transfer | Paragraph 11 | A clearance may be transferred to another legal person on application, with the transferor's written no-objection, on the same terms and for the unexpired validity; no reference to the committee is needed. |
| Expansion and change | Paragraphs 2 and 7(ii) | Capacity beyond the clearance, a change in process or technology or a new product mix needs a fresh application in Form 1; the committee decides on due diligence whether a new EIA and consultation are required. |
| Consent to establish | Section 25 Water Act 1974; Section 21 Air Act 1981 | A separate approval from the State Pollution Control Board before construction of any outlet or industrial plant; the Board decides within four months of a complete application, failing which consent under the Water Act is deemed granted (Section 25(7)). |
| Consent to operate | The same sections | Granted before commissioning once the pollution control systems are in place, for the period the State Board fixes by category, and renewed on an application made before expiry. |
Clearance and consent answer different questions. The clearance asks whether the project should be built where and as proposed; the consent asks whether a particular outlet or stack will meet the standards under the Water Act 1974, the Air Act 1981 and the Environment (Protection) Rules 1986. A project that needs both obtains the clearance first, because the consent to establish is issued in terms of it; a project below the Schedule thresholds needs only the consents. State Boards classify industries into the red, orange, green and white categories the Central Pollution Control Board harmonised in 2016, and the category drives the consent period, the inspection frequency and whether a white category unit needs consent at all. The environmental statement in Form V under Rule 14 of the Environment (Protection) Rules, due each 30 September, and the hazardous waste and extended producer responsibility returns then run alongside the half-yearly compliance reports.
Related topics
The statute, rules and portals the page relies on. Check them before acting: fees, forms and time limits change by notification.
The Act gives the Central Government and the authorities it delegates the power under Section 5 to direct the closure, prohibition or regulation of any industry, operation or process and to stop its electricity, water or other services. Since 1 April 2024 a contravention of the Act, the rules or a notification carries a monetary penalty under Section 15 in place of the earlier imprisonment, with a further penalty for each day a contravention continues and a higher scale for companies; an adjudicating officer of the rank of Joint Secretary to the Government of India or Secretary to a State Government holds the inquiry under Section 15C and the Environment Protection (Manner of Holding Inquiry and Imposition of Penalty) Rules 2024, and an appeal lies to the National Green Tribunal within 60 days under Section 15D on a pre-deposit of 10 per cent. Failure to pay within 90 days is itself an offence. The Tribunal may separately order restoration and compensation under Section 15 of its own Act, and courts have ordered demolition where construction could not be reconciled with the Notification.
Regularisation has a litigated history. A notification of 14 March 2017 opened a six-month window for violation cases to apply for clearance on penal terms, and an office memorandum of 7 July 2021 set a standard procedure for later cases. In Vanashakti v. Union of India the Supreme Court struck both down in May 2025, recalled that judgment on review in November 2025, and on 29 July 2026 held that the 2017 notification stood as a time-bound amnesty, that the 2021 office memorandum was invalid because an amnesty can be created only by a notification under Section 3 of the Act, that clearances already granted stand and pending applications are to be decided, and that no fresh application for post-facto clearance may be made. As the law now stands, a proponent that has begun work without clearance has no route to regularise it unless the Central Government issues a new, narrowly drawn notification.
Challenging a clearance before the National Green Tribunal
Any person aggrieved by the grant or refusal of an environmental clearance may appeal to the Tribunal under Section 16 of the National Green Tribunal Act 2010 within 30 days of the order being communicated, which the Tribunal may extend by up to 60 days for sufficient cause. A substantial question relating to the environment that does not arise from an appealable order goes by original application under Section 14, within six months of the cause of action, extendable by 60 days. The Tribunal applies the precautionary principle, the polluter pays principle and sustainable development (Section 20), and its orders are executable as decrees of a civil court. A further appeal lies to the Supreme Court under Section 22 within 90 days.
Related topics
The statute, rules and portals the page relies on. Check them before acting: fees, forms and time limits change by notification.
| Approval | Law and authority | When it applies |
|---|---|---|
| Forest clearance | Section 2 of the Van (Sanrakshan Evam Samvardhan) Adhiniyam 1980 (the Forest (Conservation) Act, renamed in 2023); the Central Government on the advice of the Forest Advisory Committee or the regional empowered committee, through the state forest department | Whenever forest land is to be used for a non-forest purpose; granted in two stages, with compensatory afforestation and net present value payable before the final approval. |
| Wildlife clearance | Wild Life (Protection) Act 1972; the Standing Committee of the National Board for Wild Life, after the State Board for Wild Life | Projects inside a national park or sanctuary, inside a notified eco-sensitive zone, or within the default 10-kilometre belt around a protected area where no zone has been notified (Supreme Court orders in Goa Foundation v. Union of India, 2006). |
| CRZ clearance | Coastal Regulation Zone Notification 2019 (S.O. 37(E), 18 January 2019); the State or Union Territory Coastal Zone Management Authority recommends, the Ministry decides for CRZ-I and CRZ-IV and the state authority for CRZ-II and CRZ-III | Any project in the coastal regulation zone, measured from the high tide line and along tidal water bodies; run with the environmental clearance where both apply. |
| Consent to establish and consent to operate | Section 25 Water Act 1974 and Section 21 Air Act 1981; the State Pollution Control Board or Pollution Control Committee | Every industry, operation or process that discharges effluent or emits into the air, whether or not it needs environmental clearance; four-month decision period. |
| Hazardous waste authorisation | Rule 6 of the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016; the State Pollution Control Board | Any occupier handling hazardous or other wastes; valid for five years and renewed with the consents. |
| Groundwater abstraction | Guidelines of the Central Ground Water Authority under Section 3(3) of the Environment (Protection) Act 1986; the Authority or the state groundwater body | Industries, infrastructure and mining projects that draw groundwater, with the no-objection certificate made a condition of the clearance. |
Related topics
- Prior environmental clearance
- The approval under the EIA Notification 2006 that a listed project must hold before any construction or land preparation begins, granted with conditions for the period in paragraph 9.
- Category B1 and B2
- The two sub-classes of Category B fixed at screening by the SEAC: B1 projects need an EIA report and, unless exempt, a public hearing; B2 projects are appraised on Form 1 and the pre-feasibility report or conceptual plan alone.
- Terms of Reference
- The scope of the EIA study settled at scoping by the EAC or SEAC: the impacts, baseline season, study area and special studies the report must cover, conveyed within 60 days of receipt of Form 1 or deemed final as proposed.
- Expert Appraisal Committee
- The sectoral committee of experts the Ministry constitutes for three years under paragraph 5 and Appendix VI to screen, scope and appraise Category A projects; its state counterpart is the State Expert Appraisal Committee.
- SEIAA
- The State Environment Impact Assessment Authority: a three-member body (Chairperson, Member Secretary and a member) notified by the Central Government under Section 3(3) of the Environment (Protection) Act 1986 to grant clearance to Category B projects in the state.
- Public hearing
- The meeting held by the State Pollution Control Board at or near the site under Appendix IV, after 30 days' notice, at which local residents and other concerned persons record their views on the draft EIA report before a presiding district officer.
- Environment Management Plan
- The chapter of the EIA report, and later a clearance condition, that sets out the mitigation measures, their cost, the monitoring programme and the organisation responsible for each during construction and operation.
- PARIVESH
- The Ministry's single-window portal, launched in August 2018, through which environmental, forest, wildlife and CRZ proposals are filed, tracked, appraised and decided, and on which committee agendas, minutes and clearance letters are published.
Related topics
Related topics
The statute, rules and portals the page relies on. Check them before acting: fees, forms and time limits change by notification.
- PARIVESH: single-window portal for environmental, forest, wildlife and CRZ clearances
- Ministry of Environment, Forest and Climate Change
- Environment (Protection) Act, 1986, India Code
- Water (Prevention and Control of Pollution) Act, 1974, India Code
- National Green Tribunal Act, 2010, India Code
- Central Pollution Control Board
- NABET, Quality Council of India: accreditation of EIA consultant organisations
- National Green Tribunal